Building


1.  Project Schedule Update: 1.1  Our Development Permit Application had been approved at COR “Development Permit Panel” meeting on May 16th. In general, Building Permit (BP) will be issued in 2 months after the approval of DP, then we can start the construction work. If all goes well, construction period is […]

Building Committee Monthly Briefing on 17 June 2018


1.  Project Schedule Update: 1.1  Our Development Permit Application had been approved at COR “Development Permit Panel” meeting on May 16th. In general, Building Permit (BP) will be issued in 2 months after the approval of DP, then we can start the construction work. If all goes well, construction period is […]

Building Committee Monthly Briefing on 20 May 2018


1.  Project Schedule Update: 1.1  COR Planner David verbally reply us that our application is now under City Manager final review.  If City Manager has no further comment, he will arrange our Application for discussion at COR “Development Permit Panel” meeting on May 16.  David will reply to confirm our […]

Building Committee Monthly Briefing on 15 Apr 2018